CTC Marine has completed load-out
of 8 submarine power cables at the
Prysmian factory in Naples Italy and is
now on site in the Bay of Campeche for
the Ku-Maloob-Zaap Field Development
Project, Gulf of Mexico. CTC is utilizing
the Northern River equipped with CTC's
CMROV 3, WROV and lay spread,
including cable baskets. The spread was
successfully mobilized at Tees Port UK,
in early March.
The work scope, for client Demar
Instaladora Y Constructora S.A. DE C.V,
involves the load out and transit of the
eight power cables, followed by cable
lay, trenching and survey of the power
cables, 30.8km total length, in water
depths of 70-90m.
The 111 day project is expected to
commence infield by April 2011 and
represents the first installation and
trenching project for CTC in the Gulf
of Mexico.
|